Current and past construction activities:

  • Pool concrete works are underway.
  • The three TIAB units were successfully lifted on to the roof and bolted together.
  • Roofing is progressing well. The large roof over the Curling Rink is due to start.
  • Fire proofing to structural steel elements is underway in Curling.
  • Window frames and glass are being installed in the Curling areas.
  • Painting has started to Curling internal masonry walls.

Look ahead construction activities:

  • Drywall is due to start in Curling within a couple of weeks.
  • Further concrete slabs are being prepared and will be poured over the coming weeks.

TIAB units installed:

TIAB

 

 

Pool concrete underway:

concrete