Construction Update: January 28, 2016

Current and past construction activities.

  • The structural steel frame is now complete.
  • Roofing insulation has now started.
  • The remaining 2nd floor and roof deck is in progress and will be completed within a few weeks.
  • Outside wall panels are still in progress.

Look ahead construction activities.

  • Window frames will start to be installed over the coming weeks.
  • TIAB units will be lifted towards the end of February (date to be confirmed).
  • Fire spray to structural beams and deck will start shortly in Curling.

Structural steel completeConstruction Update  280116 1

 

 

 

Roof insulation in progress

Construction Update  280116 2