Construction Updates

Cochrane’s new aquatic and curling/multi-sport centre is being built at the Spray Lake Sawmills Family Sports Centre, 800 Griffin Rd E. Construction updates are posted below:

Watch the construction on our four webcams:
Webcam 1
Webcam 2
Webcam 3
Webcam 4

  • Construction Update: May 30, 2016

    Current and past construction activities. Construction of the curling rink is now complete and is currently being wet cured. Hoarding has been erected inside the existing lobby, ceilings have been removed and electrical and plumbing works are being installed within the ceiling space. The large barrel roof over the pool is being insulated and water

    Read more...
  • Construction Update: March 31, 2016

    Current and past construction activities. Pool concrete works are still underway. The curling rink ceiling is nearly painted and preparations are being made for the rink slab. Trenching and duct installation for incoming power is underway. The main entrance window frame is nearly complete and glass is now being installed. The aquatics washrooms and change

    Read more...
  • Construction Update: February 29, 2016

    Current and past construction activities: Pool concrete works are underway. The three TIAB units were successfully lifted on to the roof and bolted together. Roofing is progressing well. The large roof over the Curling Rink is due to start. Fire proofing to structural steel elements is underway in Curling. Window frames and glass are being

    Read more...