Construction Update: December 22, 2015

Christmas 2015 Wrap Up Construction Update. We’ve had a busy year here on site with lots of activity and great progress. Here are some of the highlights achieved so far and some of the work we will be doing in the New Year. Work complete or in progress: Existing soils have been reconditioned and prepared

Construction Update: December 4, 2015

Current and past construction activities: External sanitary, storm and water are complete. Site grading has started. Roofing works have started over and around the curling rink area. Structural steel for the Aquatics portion of the building is underway. Look ahead construction activities: The feature staircase for the main lobby is being fabricated and nearly ready

Construction Update: October 30, 2015

Current and past construction activities: Excavations for incoming water has started and the grass has been stripped from the adjacent field. Underground plumbing to the Aquatics shower areas is nearing completion. Envelope panels have been installed around the Curling Rink. Look ahead construction activities: Structural steel over the pool portion of the building will start

Construction Update: October 9, 2015

Current and past construction activities. Further concrete has been poured to the 2nd level deck designated for future tenants. Underground plumbing for the Aquatics washrooms, showers and change rooms is being installed at present. Reinforcement is complete at the main entrance lobby slab and is now ready for concrete next week. Look ahead construction activities.

Construction Update: September 11, 2015

Current and past construction activities. Roof and level 2 steel deck is being installed at the Aquatics shower / locker room areas. Curling Rink header trench is currently being formed. Masonry and steel stud walls are both in progress in the Curling Rink. Look ahead construction activities. Further slabs will be poured in the main

Construction Update: August 27, 2015

Current and past construction activities. • 95% of the underground plumbing and electrical work in the Curling Rink is complete. • Concrete has been poured to the 1st and 2nd floors in the Curling Rink. • Structural steel at the main entrance lobby is very close to being completed. Look ahead construction activities. • Internal masonry and steel

Construction Update: August 5, 2015

Highlights of past construction activities. Underground plumbing and electrical work is well underway in the Curling Rink. Perimeter masonry walls have started around the Curling Rink. The Curling Rink level 2 mezzanine deck has been completed. Look ahead construction activities. Curling Rink ground floor concrete slab will soon be prepared for concrete. Structural steel to

Construction Update: July 10, 2015

Highlights of past construction activities. Upper level concrete footings are nearly complete inside the Aquatics portion of the building. Concrete work to the below ground mechanical room is in progress and starting to rise out of the ground. Further backfill and compaction has taken place inside and outside of the building to bring the site

Construction Update: June 19, 2015

Highlights of past construction activities. Concrete footings are progressing very well in the Aquatics portion of the project. Formwork has started on the below ground mechanical room footings and sump raft slab. The Curling Rink structural steel frame is nearly complete with the last of the 100ft long trusses being erected yesterday. Look ahead construction

Construction Update: June 1, 2015

Highlights of past construction activities: The first phase of back fill and compaction is complete. Concrete footings and columns are 100% complete in the Curling Rink. Formwork has commenced in the Aquatics portion of the project. Look ahead construction activities: Foundations for the deep mechanical room and sump will commence shortly. Structural steel erection has