Construction Update: April 29, 2016

Current and past construction activities.
The curling rink is now being constructed with the placement of sand and heating pipes.
Masonry walls in the aquatics change rooms are being built and are well underway.
Demolition of Pats café walls and the kid’s ball pit walls are progressing well.
The main lap pool in the aquatics has been graded and being excavated for piping.

Look ahead construction activities.
Main power cable distribution is due to start next week.
External works including final grading and paving is due to start next week.

Curling rink heating pipes installed on sand.

Construction Update  April 29, 2016-1

 

 

 

Aquatic washroom walls being built.

Construction Update  April 29, 2016-2